Project Documents Updation 3 years 5 months ago #24376

  • Parkash Pant
  • Parkash Pant's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Does updating project documents require going through Perform Integrated Change Control? I am confused because, in the Control Quality lesson, Cornelius first mentioned that change requests are not needed for project documents, and then in Outputs, he mentioned that we need change requests to update project documents?

Project Documents Updation 3 years 5 months ago #24381

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 820
  • Karma: 17
  • Thank you received: 114
My view is that it depends on the document. Something like the project schedule, which is updated regularly, or the risk and issue registers I wouldn't put through change control because they change too frequently and are working documents. Other documents, like the business case, project charter etc that have formally been approved and form part of the project records about what is authorised to be worked on - those I would put through change control.
---
Elizabeth Harrin
Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

Project Documents Updation 3 years 5 months ago #24393

  • Parkash Pant
  • Parkash Pant's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Thank you for the clarification. However, if they ask us in the exam, should I go with "no change requests" for project documents update since they are bound to be updated as the project progress?

Project Documents Updation 3 years 5 months ago #24404

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 820
  • Karma: 17
  • Thank you received: 114
I'd say my 'go to' response would be to avoid multiple choice answers that state 'no' or 'never' because there are always some situations that need a different approach. Some documents will use change control.
---
Elizabeth Harrin
Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinCoy Studer

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login