Hi,
For the question on project constraints as shown below, what is the difference between answers B & C? Why is cost right and not budget? Would really appreciate it if someone could clarify this.
Thank you,
Kind regards,
Priya
Yesterday's Answer
Which of the following are the project constraints?
A.) Scope, Schedule, Budget, Personnel, Quality, Risk
B.) Scope, Schedule, Budget, Resources, Quality, Risk
C.) Scope, Schedule, Cost, Resources, Quality, Risk
D.) Scope, Schedule, Cost, Personnel, Quality, Risk
C.) is correct. The competing project constraints that you as the project manager must balance are Scope, Quality, Schedule, Cost, Resources, and Risk.