How is a warranty that extends beyond the end of a project accounted for? 3 weeks 6 days ago #22164

  • Ryan Klopp
  • Ryan Klopp's Avatar Topic Author
  • Online
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
I'm confused as to if a project can end when there is an outstanding warranty on a deliverable, and if the project can end when there is an outstanding warranty then how are the costs associated with correcting the defect accounted for and recorded in the project budget ?

How is a warranty that extends beyond the end of a project accounted for? 3 weeks 2 days ago #22220

  • Kyle Kilbride, PMP
  • Kyle Kilbride, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 18
  • Thank you received: 6
In my experience if a product is produced by a supplier the warranty costs would be borne by the supplier itself (the business), not the individual project (depending on the specific contract). Warranty is considered a cost of nonconformance, but depending on the warranty period these issues could be found long after the project is closed. Therefore, it is necessary for the business (of the supplier) to be prepared to support these claims as they arise. The supplier should build this cost (or a factor of it) into their price.
Regards,
Kyle Kilbride, P.Eng, PMP
PMPrepCast Community Moderator
The following user(s) said Thank You: Ryan Klopp

How is a warranty that extends beyond the end of a project accounted for? 2 weeks 2 days ago #22366

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 234
  • Karma: 13
  • Thank you received: 75
Ryan,

I'm a little late to this discussion. Kyle is correct. Warranty work that extends to the life of the project is accounted for under "operations" as opposed to "project." In a real setting, a business making a widget will perform testing on the widget to fine the mean time between failures, and then make a decision based on that information to determine if they need an insurance policy or just absorb the cost of replacing or repairing the widget. That is built into the price of the widget.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPMohammad Alharbi, PMP, PMI-ACPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Get PMP Exam Ready in Just Four Weeks! Join the Live PMP Blended Training Course Starting August 10. Click to learn more...