Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Project Management Plan Update Versus CR

Project Management Plan Update Versus CR 3 weeks 4 days ago #21522

  • Patrick Sweet
  • Patrick Sweet's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Hi all,

I'm confused as to why in "Manage Project Knowledge", one of the outputs is "PMP Updates". Shouldn't the output be "Change Request", since an approved PMP is a controlled document?

In 4.4.3.2, the PMBOK says "Any change to the project management plan goes through the organization's change control process via a change request. Any component of the project management plan may be updated as a result of this process." Isn't this telling me directly that the output should be a CR?

Thanks,
Pat

Project Management Plan Update Versus CR 3 weeks 4 days ago #21539

  • Eric Wanyutu Kahiga, PMP
  • Eric Wanyutu Kahiga, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 54
  • Karma: 4
  • Thank you received: 17
Hi, Patrick.

Manage Project Knowledge is defined as the process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning. This definition implies that new knowledge that will be vital for this and other future projects will be created as the project work continues.

The project management plan (PMP) with all it’s a components is a living document that continues to change as the project goes on. From it, templates such as the WBS and its associated dictionary can be extracted for future projects and as such (PMP) updates are included as part of the outputs. You are of course correct when you point out that change requests are required to change the (PMP). We can perhaps conclude that PMI in its wisdom is using the principle of “abundance of caution” to ensure that you do both the change requests and PMP updates. (PMBOK 6th Edition, Pg. 70)

I hope that helps.

Project Management Plan Update Versus CR 3 weeks 4 days ago #21542

  • Devin
  • Devin's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 48
  • Karma: 5
  • Thank you received: 25
I agree with Eric, you may not get a satisfactory answer on this, but on page 70: "Figure 4-1 provides an overview of the Project Integration Management processes. The Project Integration Management processes are presented as discrete processes with defined interfaces while, in practice, they overlap and interact in ways that cannot be completely detailed in the PMBOK® Guide."

Looking on page 596 are closely linked and that process does create change requests. So perhaps the change request is not emanating from the manage project knowledge process, but rather the output is a new project document we need to manage (a new version).

Interesting catch - because most of the other executing processes do produce change requests!
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPMohammad Alharbi, PMP, PMI-ACPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on July 18/19 for just $199. Click to learn more... OR Click to watch a free session...