fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Implementing a risk response necessitates a change request ?

Implementing a risk response necessitates a change request ? 5 years 11 months ago #21203

  • Ihab Abdelaziz
  • Ihab Abdelaziz's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Hello,
When implementing a risk response as a reaction to an identified trigger, do we still need to submit a change request? Even though the appropriate contingency reserve was previously assigned for such risk?
How to react in this situation confuses me, kindly advise.
Thanks in advance,
Ihab Abdelaziz

Implementing a risk response necessitates a change request ? 5 years 11 months ago #21205

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 598
  • Karma: 40
  • Thank you received: 169
Ihab,

Implementing a response to an identified (and therefore planned) risk does not require a change request. However, if you find your response is unsatisfactory and further response will require a change in one of the baselines, then a change request is warranted.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP

Implementing a risk response necessitates a change request ? 5 years 11 months ago #21254

  • Ihab Abdelaziz
  • Ihab Abdelaziz's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Thanks Harry for your reply.

But what if the implemented response (the 1st planned response not a 2nd or further response) will affect parts of the baselines that weren't affected before implementing the response, do we still need to submit a change request?
pardon my question.

Ihab

Implementing a risk response necessitates a change request ? 5 years 11 months ago #21256

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 598
  • Karma: 40
  • Thank you received: 169
Ihab,

Should the response be unsatisfactory to cover the risk and further response will affect any baseline, a change request is required.

Perhaps a better, more broad way of thinking about it is that if anything happens to a project (or you're going to do something to a project) once the project is in motion, a change request is necessary.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP

Implementing a risk response necessitates a change request ? 5 years 11 months ago #21403

  • Ihab Abdelaziz
  • Ihab Abdelaziz's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Thats clear, thanks a lot.

Ihab

Implementing a risk response necessitates a change request ? 5 years 11 months ago #21406

  • Neha Talavdekar
  • Neha Talavdekar's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Since Risk Response is already in place appropriate cost/schedule buffers are added to the plan. So cost/schedule baseline already has it included. So no CR is needed.
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMP, CSM, DFFS Black BeltElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login