fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Activity duration range estimate with standard deviation

Activity duration range estimate with standard deviation 6 years 2 weeks ago #20919

  • Ruby F
  • Ruby F's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Hi guys - same again, my exam is tomorrow and I have a quick question.

With calculation the range of estimated duration +- standard deviation, if we get a question like this on exam how do we know whether to use the triangular formula or the PERT formula.

Thanks to anyone

Activity duration range estimate with standard deviation 6 years 2 weeks ago #20935

  • Eric Wanyutu Kahiga, PMP, PMI-ACP
  • Eric Wanyutu Kahiga, PMP, PMI-ACP's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 84
  • Karma: 4
  • Thank you received: 28
Hi Ruby.

Usually, the exam question will state which method to use.

Once again, I wish you the very best in your exam.
Eric Wanyutu
The following user(s) said Thank You: Ruby F
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMP, CSM, DFFS Black BeltElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login