TOPIC: PMB When Using EVM

PMB When Using EVM 1 month 2 weeks ago #20607

  • Alexander Martin
  • Alexander Martin's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Question:

Module 7.03 Determining Budget Part 2 (at 19:28) states that "In EVM, Planned Value is the PMB" but in the PMBOK Guide (pg. 254) it states "For projects that use EVM, the cost baseline is referred to as the PMB". Does that mean that Planned Value means the same thing as Cost Baseline in EVM? Can someone help me understand these statements a little better?

Thank you!
- Alexander M.
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPMohammad Alharbi, PMP, PMI-ACPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPFelix Kamanga, PMPChan Rampersaud

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login