fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Risk Response

Risk Response 6 years 3 months ago #19849

  • Anantha Narayanan Santhanagopalan
  • Anantha Narayanan Santhanagopalan's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 39
  • Karma: 3
  • Thank you received: 7
Does Project Manager need to submit change request to implement a risk response for which he already has a contingency reserve allocated?

To my knowledge, if a risk for which we already have a risk response plan we need not go through change request to use contingency reserve. Can anyone confirm please?

Risk Response 6 years 3 months ago #19850

  • googlesmart
  • googlesmart's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 17
  • Karma: 1
  • Thank you received: 10
Correct, if it is identified risk.
The following user(s) said Thank You: Anantha Narayanan Santhanagopalan
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMP, CSM, DFFS Black BeltElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login