TOPIC: Risk Response

Risk Response 9 months 3 weeks ago #19849

  • Anantha Narayanan Santhanagopalan
  • Anantha Narayanan Santhanagopalan's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 39
  • Karma: 3
  • Thank you received: 7
Does Project Manager need to submit change request to implement a risk response for which he already has a contingency reserve allocated?

To my knowledge, if a risk for which we already have a risk response plan we need not go through change request to use contingency reserve. Can anyone confirm please?

Risk Response 9 months 3 weeks ago #19850

  • googlesmart
  • googlesmart's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 17
  • Karma: 1
  • Thank you received: 10
Correct, if it is identified risk.
The following user(s) said Thank You: Anantha Narayanan Santhanagopalan
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login