TOPIC: Finla Procurement closure is part of control procurement or close project( PMP )

Finla Procurement closure is part of control procurement or close project( PMP ) 9 months 5 days ago #19686

  • San C
  • San C's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
In RM chart,

Attachments:

Finla Procurement closure is part of control procurement or close project( PMP ) 9 months 5 days ago #19689

  • San C
  • San C's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Can someone please answer asap.

Finla Procurement closure is part of control procurement or close project( PMP ) 9 months 4 days ago #19690

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 279
  • Karma: 17
  • Thank you received: 94
Closed contracts are an output of Project Procurement Management, "Control Procurement." See PMBOK 6th, Figure 12.1 and Section 12.3.3.1.

Always go to source material (e.g. PMBOK Guide) as opposed to derivative works when looking for an answer.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login