fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Finla Procurement closure is part of control procurement or close project( PMP )

Finla Procurement closure is part of control procurement or close project( PMP ) 4 years 3 months ago #19686

  • San C
  • San C's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
In RM chart,

Attachments:

Finla Procurement closure is part of control procurement or close project( PMP ) 4 years 3 months ago #19689

  • San C
  • San C's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Can someone please answer asap.

Finla Procurement closure is part of control procurement or close project( PMP ) 4 years 3 months ago #19690

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 457
  • Karma: 27
  • Thank you received: 144
Closed contracts are an output of Project Procurement Management, "Control Procurement." See PMBOK 6th, Figure 12.1 and Section 12.3.3.1.

Always go to source material (e.g. PMBOK Guide) as opposed to derivative works when looking for an answer.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login