TOPIC: Need help with a Quick Question...

Need help with a Quick Question... 6 years 4 months ago #19464

  • Christian Bass
  • Christian Bass's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 0
Is a Responsibility assignment matrix an output of any of the processes?
I can find definitions and examples but I'm not sure where this comes from in the grand scheme of things.

Thanks.

Need help with a Quick Question... 6 years 4 months ago #19469

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 598
  • Karma: 40
  • Thank you received: 169
Christian,

No. It is a tool/technique of "Plan Resource Management." (PMBOK 6th ed, page 312 is the first mention of the RAM).

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMP, CSM, DFFS Black BeltElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login