Registration Process 4 years 3 months ago #19446

  • Adebayo Ifebajo
  • Adebayo Ifebajo's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Hey Ladies and Gentlemen,

I need some guide here. I was trying to fill the documents for my registration. After putting in all my hours and years I have the attached.

It says I need 882.02 hours.

Could some please walk me through the registration process.

Much appreciated.
Bayo
Attachments:

Registration Process 4 years 3 months ago #19453

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 24
  • Thank you received: 98
Hi Adebayo,

From the screenshot, it looks like only 3617 hours were recognized by PMI. Did they give you a justification on why they cannot recognize all of your hours? Can you post the hours breakdown for us?
Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin

Registration Process 4 years 3 months ago #19459

  • Adebayo Ifebajo
  • Adebayo Ifebajo's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Thank you very much Joe.

The hours I put in are as follows:
Initiating: 600
Planning: 800
Executing: 1700
Monitoring and Control: 1100
Closing: 400

The Project was from May 2010 to Sep 2017

I look forward to your response.

Thank you very much

Adebayo

Registration Process 4 years 2 months ago #19478

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 24
  • Thank you received: 98
Hi Adebayo,

In order for your project experience to be eligible, it has to be within the last 8 years.

I don't know how the math works, but the system must have ignored the hours from 2010.

Hope this helps
Joe
Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
The following user(s) said Thank You: Adebayo Ifebajo

Registration Process 4 years 2 months ago #19488

  • Adebayo Ifebajo
  • Adebayo Ifebajo's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Thank you very much Joe. This surely helps.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login