I created these questions based on experience and a lessoned learn standpoint. I mainly just wanted to gain insight from professionals on when to contact sponsor, change schedule, issue a change request, while reporting issues accordingly.
1. If a software engineer discovered a process that was overlooked and needs to be implemented but could add two months on the schedule causing a delay.
What should the PM do next?
A. initiate a change control process
B. Contact the Sponsor
C: adjust schedule baseline
D. Crash schedule
2. If an engineer discovers and repaired an issue in testing without submitting a change request.
What should that PM do next?
A. Initiate a change control
B. Record it is RIsk Register
C. Record it in Lesson Learned
D. Do nothing