fbpx

Reply: Exam Question Help with Explanation

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Exam Question Help with Explanation

Max. showing the last 6 posts - (Last post first)
4 years 3 months ago #19313

Patrick Smith

Patrick  Smith's Avatar

Hey Corneluis,

I created these questions based on experience and a lessoned learn standpoint. I mainly just wanted to gain insight from professionals on when to contact sponsor, change schedule, issue a change request, while reporting issues accordingly.

~Pat
4 years 3 months ago #19312

Cornelius Fichtner

Cornelius Fichtner's Avatar

Patrick,

Please give credit to the original creator of these sample questions. Where are they from and are you permitted to post them here publicly?

Thank you.
4 years 3 months ago #19298

Patrick Smith

Patrick  Smith's Avatar

1. If a software engineer discovered a process that was overlooked and needs to be implemented but could add two months on the schedule causing a delay.

What should the PM do next?

A. initiate a change control process
B. Contact the Sponsor
C: adjust schedule baseline
D. Crash schedule

2. If an engineer discovers and repaired an issue in testing without submitting a change request.
What should that PM do next?

A. Initiate a change control
B. Record it is RIsk Register
C. Record it in Lesson Learned
D. Do nothing