fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Formula Exam Question Clarification

Formula Exam Question Clarification 4 years 4 months ago #19256

  • Ken Fraser
  • Ken Fraser's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
I would like an explanation as to how it is determined from this question below that there was an issue to justify the EAC formula used.

Question 10: PV = 100, EV = 105, BAC = 400, AC = 102 and CV = 3? What is the
Estimate to Complete (ETC) if work will continue at the planned rate?
A) 298
B) 300
C) 305
D) 295
: The formula for calculating the ETC is: ETC = EAC – AC. First, since
estimate at completion does not exist, you must calculate it using the formula
EAC = AC + (BAC – EV) = 102 + (400 – 105) = 397. Once you have the EAC,
you plug the values into the formula ETC = EAC – AC giving you ETC = 397 –
102 = 295

Formula Exam Question Clarification 4 years 4 months ago #19293

  • Vamshi Sekar
  • Vamshi Sekar's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
I think the formula used is inappropriate. I think it should be BAC/CPI.

Formula Exam Question Clarification 4 years 4 months ago #19294

  • Ken Fraser
  • Ken Fraser's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
I agree, and that is how I responded initially.

Thanks
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login