What's EMV (BEFORE COSTS)? 4 years 4 months ago #19170

  • Eric Hu
  • Eric Hu's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 17
  • Thank you received: 1
On PMBOK page 435, in Figure 11-15, below EMV calculation of "Build New Plant" there is a parenthesis mentioning "before costs".
What does "before costs" mean? in Net Path Values it actually considers cost by subtracting investment($120M), so I think it should be "after costs".
Any suggestions?