4 years 5 months ago #18821

Tracy Shagnea, PMP

Tracy Shagnea, PMP's Avatar

I'm with Tyler. The best, most specific and correct answer is "C".

Good luck!
Tracy
4 years 5 months ago #18797

Tyler Wood

Tyler Wood's Avatar

I would choose C. The PMP exam asks you to choose the BEST correct answer. While C & D are both correct, C is the BEST correct answer as it is the most specific part of the Project Management Plan which deals with Risk.
4 years 5 months ago #18792

Michael Lawing

Michael Lawing's Avatar

Greetings everyone,

I am taking my PMP exam tomorrow (2nd attempt) and am fairly confident I will pass, but I just thought of a relic of the past that I believe really hurt me the 1st time.

Let us take a look at a sample question below (Note: this was not a question verbatim on the PMP exam when I first took it, because I do not fully remember).

Q: A project manager wants to find out how management activities regarding risks will be structured and performed. Where should the project manage look to find this information?

A. Risk Register
B. Cost baseline
C. Risk Management Plan
D. Project Management Plan

Obviously, "A" and "B" can be eliminated. Initially, I think "C" is the answer, but then I think, "Wait a minute. Risk Management Plan is a part of the Project Management Plan; thus, the answer is 'D.'"

My question is, is my thought process correct, or am I to correct the most appropriate (or "best") answer?