TOPIC: Rolling Wave Plannin vs. Iterative Schedulin w/ backlog vs. On-demand schedulin

Rolling Wave Plannin vs. Iterative Schedulin w/ backlog vs. On-demand schedulin 7 years 1 month ago #18569

  • J
  • J's Avatar Topic Author
  • Visitor
  • Visitor
Hi everyone,

I am having difficulty distinguishing the 3: Rolling Wave Planning, Iterative Scheduling with backlog, and On-demand scheduling.
I have read the definitions and explanations in the PMBOK, but still - I can't figure out the major difference between the 3.

Can anyone help?

This is what I deciphered in simple terms:
Rolling Wave - Work accomplished near term planned in detail, while future work is planned at a higher level
Iterative Scheduling with a backlog - Completes work on backlog? (*confused*)
On-demand Scheduling - Pulls work from backlog depending on resources available (KanBan)
Moderators: Yolanda Mabutas, Markus Kopko, Mary Kathrine Padua, Professor Kevin Reilly, John Paul Bugarin, Anusha Jayaram, Harry Elston, Jean Kwanda, Neil Baghurst PMP, Elena Zelenevskaia, Erik Smith, Joseph Flanders, Pablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login