TOPIC: Dependency/ logical relationship between activities

Dependency/ logical relationship between activities 3 months 21 hours ago #18471

  • KADIR VEDACHALAM
  • KADIR VEDACHALAM's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Hello Experts,
Requesting direction for attached illustration from PMBOK 6. If the dependency shown is FS (Finish to Start), practically, the 2nd activity cannot start before the 1st activity finishes (can have only a lag).
Please Help!
Attachments:
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily RiveraLisa Sweeney PMPHarry ElstonMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on December 21/22 for just $179. Click to learn more... OR Click to watch a free session...