close project /phase 7 years 1 month ago #18186

  • Archana
  • Archana 's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 17
  • Thank you received: 0
practice test 5 - ques 61

says close project /phase is always the last process to perform....what does it mean..??
pmbok says process is done once or at predefined points.
pls explain

close project /phase 7 years 1 month ago #18192

  • Donald Terry
  • Donald Terry's Avatar
  • Offline
  • Administrator
  • Administrator
  • Posts: 41
  • Karma: -9
  • Thank you received: 18
Hi Archana,

All projects should be closed out. The last project management process performed for all projects should be the Close Project or Phase process. This is true even if the project is terminated before completion. If a project is broken down in phases, the Close Project or Phase process will be conducted at the end of each phase and at the end of the project.

I hope that helps as you prepare for your exam.
Donald Terry, MBA, PMP, PMI-ACP
Independent contractor at OSP International LLC
Moderators: Yolanda Mabutas, Markus Kopko, Mary Kathrine Padua, Professor Kevin Reilly, John Paul Bugarin, Anusha Jayaram, Harry Elston, Jean Kwanda, Neil Baghurst PMP, Elena Zelenevskaia, Erik Smith, Joseph Flanders, Pablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login