Hey Donald, thanks for your reply. So just to confirm, I should just go with the understanding that
1) in the Close Project/Phase process, you CONFIRM that scope/deliverables were accepted
2) in the Validate Scope process, you OBTAIN acceptance of scope/deliverables.
P.S. Is there any way to request that the PMI update their wording on that packet? If what we say above it true, the packet is flat-out using the wrong terminology and many students are likely getting these questions as a direct result.
Thanks,
Ally