All, I am partly confused on the Lessons Learned Register. Isn't it while the project is in play you would add information tot he register but when the project is complete it would be the lessons learned repository? The question I had stated that if you are in a multiphase project you would add lessons learned to the repository if you were in other phases. Is that the case? Could someone clarify this?

Lessons Learned Register vs Lessons Learned 6 months 1 week ago #17584

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 84
  • Karma: 3
  • Thank you received: 17
PMBOK page 104 section 4.4.3.1 last paragraph stated that "at the end of a project or phase", the information in the Lessons Learned Register will be transferred to Lessons Learned Repository.
Updating the lessons learned register is an ongoing process from the start to the end of the project or phase, once you complete the project or phase, you will then transferred to the lessons learned repository.
The following user(s) said Thank You: Daniel Kokkos
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily RiveraLisa Sweeney PMPHarry ElstonMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on December 21/22 for just $179. Click to learn more... OR Click to watch a free session...