Where, or in what process, is the performance measurement baseline set/developed? I understand it is a part of the project management plan, however, is this set by project sponsor?

PMB 1 year 2 months ago #17519

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 84
  • Karma: 4
  • Thank you received: 17
Performance measurement baseline (PMB) are the 3 baselines combined: Scope, Schedule and Cost. Each of these baselines are performed in their respective processes and then integrated into "Develop Project Management Plan" process. PMB gets updated as the project progresses.
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login