TOPIC: PMB

PMB 7 years 2 days ago #17502

  • Daniel Diaz
  • Daniel Diaz's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Where, or in what process, is the performance measurement baseline set/developed? I understand it is a part of the project management plan, however, is this set by project sponsor?

PMB 6 years 11 months ago #17519

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 84
  • Karma: 5
  • Thank you received: 21
Performance measurement baseline (PMB) are the 3 baselines combined: Scope, Schedule and Cost. Each of these baselines are performed in their respective processes and then integrated into "Develop Project Management Plan" process. PMB gets updated as the project progresses.
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMP, CSM, DFFS Black BeltElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login