TOPIC: Work packages VS Define activites

Work packages VS Define activites 7 years 1 week ago #17411

  • Gaurav Saxena
  • Gaurav Saxena's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 27
  • Thank you received: 0
Hi All,
looking for another understanding on Work packages ( which is lowest package of WBS ) and activity . Work package is not a activity ? or it is group of activity ? Kindly help.

Thanks

Work packages VS Define activites 7 years 2 days ago #17500

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 84
  • Karma: 5
  • Thank you received: 21
PMBOK page 181 stated the key benefit for Define Activities process is that "it decomposes work packages into schedule activities...", therefore, it is a series of activities to complete the work package. For example, you have a work package called "Chapter 5 Project Scope Management Exam Readiness" and the activities are:
1. Listen to PrepCast for section 5.1 to 5.6
2. Read PMBOK for section 5.1 to 5.6
3. Do exam questions for Chapter 5
4. Revise incorrect questions

Hope this explanation helps.
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMP, CSM, DFFS Black BeltElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login