TOPIC: Work packages VS Define activites

Work packages VS Define activites 1 week 5 days ago #17411

  • Gaurav Saxena
  • Gaurav Saxena's Avatar Topic Author
  • Away
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 16
  • Thank you received: 0
Hi All,
looking for another understanding on Work packages ( which is lowest package of WBS ) and activity . Work package is not a activity ? or it is group of activity ? Kindly help.

Thanks

Work packages VS Define activites 4 days 16 hours ago #17500

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 74
  • Thank you received: 13
PMBOK page 181 stated the key benefit for Define Activities process is that "it decomposes work packages into schedule activities...", therefore, it is a series of activities to complete the work package. For example, you have a work package called "Chapter 5 Project Scope Management Exam Readiness" and the activities are:
1. Listen to PrepCast for section 5.1 to 5.6
2. Read PMBOK for section 5.1 to 5.6
3. Do exam questions for Chapter 5
4. Revise incorrect questions

Hope this explanation helps.
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily Rivera

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login