In Lession L07.03: Determine Budget - Part 2, 21:19
"Which of the following does not need a change request to modify its value after it is approved?"
"The correct answer is B: Mangement Reserve"
However, in Self_Assessment_07_Cost, the explanation under Question 13 says "B.) ... but increasing manager reserve requires a change request...".
So is change request required to change managment reserve?