TOPIC: Work Performance Information

Work Performance Information 4 years 10 months ago #17336

  • Nicole DMello
  • Nicole DMello's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Is Work Performance Information an input or output for Monitor and Control Project Work process?
I am getting conflicting information from different sources.

Work Performance Information 4 years 10 months ago #17338

  • Giuliana Giancotta
  • Giuliana Giancotta's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Karma: 1
  • Thank you received: 1
Work performance information is an output of all processes in the M/C processes groups except M/C project work and Perform Integrated change control.
The following user(s) said Thank You: Nicole DMello
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login