WBS is in the Scope Baseline (refer to PMBOK page 161). Scope Baseline is the approved version of the scope statement, WBS and the WBS dictionary. Scope Baseline is an input to Define Activities.

A project charter has the summary milestone schedule (refer toPMBOK page 81) which is used as an input to Plan Schedule Management process. Schedule Management Plan is one component of the Project Management Plan which is an input to Define Activities.
4 years 10 months ago #17330

Edmund Fong

Edmund Fong's Avatar

As title

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login