You only need to submit change requests when there is a variance between planned vs. actual performance that impact your baselines. In your change request, you can indicate what technique you are using to bring your baselines back.
Do you need to submit change requests for both fast-tracking and crashing, or only when those techniques will change the schedule baseline and perhaps other constraints?