TOPIC: Change requests for schedule compression techniques

Change requests for schedule compression techniques 1 year 3 months ago #17218

  • Ben Chalfie
  • Ben Chalfie's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 0
Do you need to submit change requests for both fast-tracking and crashing, or only when those techniques will change the schedule baseline and perhaps other constraints?

Change requests for schedule compression techniques 1 year 3 months ago #17261

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 84
  • Karma: 4
  • Thank you received: 17
You only need to submit change requests when there is a variance between planned vs. actual performance that impact your baselines. In your change request, you can indicate what technique you are using to bring your baselines back.
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPMohammad Alharbi, PMP, PMI-ACPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Get PMP Exam Ready in Just Four Weeks! Join the Live PMP Blended Training Course Starting August 10. Click to learn more...