TOPIC: Change requests for schedule compression techniques

Change requests for schedule compression techniques 1 month 2 weeks ago #17218

  • Ben Chalfie
  • Ben Chalfie's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 0
Do you need to submit change requests for both fast-tracking and crashing, or only when those techniques will change the schedule baseline and perhaps other constraints?

Change requests for schedule compression techniques 1 month 1 week ago #17261

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 80
  • Thank you received: 15
You only need to submit change requests when there is a variance between planned vs. actual performance that impact your baselines. In your change request, you can indicate what technique you are using to bring your baselines back.
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily Rivera

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
21-Jun-2019: Free PMP Exam Coaching Webinar with Dan Ryan Register Now...