TOPIC: Stakeholder engagement assessment matrix

Stakeholder engagement assessment matrix 4 years 11 months ago #17172

  • Ben Chalfie
  • Ben Chalfie's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 0
Is the stakeholder engagement assessment matrix a part of the stakeholder management plan? Either way, are you required to update it or reference it when managing and monitoring stakeholder engagement?

Stakeholder engagement assessment matrix 4 years 11 months ago #17204

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 84
  • Karma: 5
  • Thank you received: 21
Just a quick note. There is NO stakeholder management plan but rather Stakeholder Engagement Plan. Stakeholder engagement assessment matrix is not a part of the Stakeholder Engagement Plan. The matrix will get updated throughout the project to reflect any changes in stakeholder engagement levels.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login