TOPIC: Float Effect on Finished Date Calculation

Float Effect on Finished Date Calculation 1 year 6 months ago #17027

  • Pen2rac
  • Pen2rac's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
A project manager tracks the work of team members using a network logic diagram. Which effect will the presence of an actual finish date have on the calculation of float for the finished activity?

o Finished activities have only float left when they have been completed on schedule.
o Calculating free float and total float is generally not reasonable for finished activities.
o When an activity has been finished, total float gets often converted to become free float.
o When an activity has been finished, float gets often converted to become slack.

Float Effect on Finished Date Calculation 3 weeks 20 hours ago #23685

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
calculation of free or total float on finished activities is not reasonable
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login