TOPIC: Change request requirement!

Change request requirement! 1 year 6 months ago #16997

  • Sharan Correa
  • Sharan Correa's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hi,

If an attempt is made to amend or modify any project document / project artifact which is not a part of configuration control , then it should be processed by raising a CR (Type: Update ) or should be
done outside integrated change control?

Change request requirement! 1 year 6 months ago #17000

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 228
  • Karma: 18
  • Thank you received: 71
Hi Sharan

If a project document was not identified in Configuration Control, a change request is not required.

For example, the issue log is typically not under Configuration Control, you don't need to submit a change request for changing the color of the fonts in the document.

Hope this helps,
Joe
Toronto-based project manager, I specialize in Capital Projects and Digital Transformation Projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login