TOPIC: Contingency cost in Bussines case ?

Contingency cost in Bussines case ? 1 year 5 months ago #16972

  • Nachiketa
  • Nachiketa's Avatar Topic Author
  • Visitor
  • Visitor
Looking for an answer.

which cost should be calculated /included in Business Case ? can we include contingency cost in business case.?

Contingency cost in Bussines case ? 1 year 5 months ago #16979

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 221
  • Karma: 18
  • Thank you received: 69
Hi Nachiketa,

In the PMP exam standpoint, the purpose of the business case is to determine whether the expected outcomes of the project justify the required investment. In the PMBOK 6 there is no mentioning of cost in the business case (pg 30-32), therefore the project manager is not required to calculate any costs at this stage.

Hope this helps,
Joe
Toronto-based project manager, I specialize in Capital Projects and Digital Transformation Projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login