fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Contingency cost in Bussines case ?

Contingency cost in Bussines case ? 7 years 1 month ago #16972

  • Nachiketa
  • Nachiketa's Avatar Topic Author
  • Visitor
  • Visitor
Looking for an answer.

which cost should be calculated /included in Business Case ? can we include contingency cost in business case.?

Contingency cost in Bussines case ? 7 years 1 month ago #16979

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 26
  • Thank you received: 99
Hi Nachiketa,

In the PMP exam standpoint, the purpose of the business case is to determine whether the expected outcomes of the project justify the required investment. In the PMBOK 6 there is no mentioning of cost in the business case (pg 30-32), therefore the project manager is not required to calculate any costs at this stage.

Hope this helps,
Joe
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMP, CSM, DFFS Black BeltElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login