fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Residual Risk Cost

Residual Risk Cost 5 years 1 week ago #16820

  • Najeeb Safi
  • Najeeb Safi's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Where do we account for Residual Risk Cost? is it part of Contingency reserve or management reserve? Chapter 11.5

Residual Risk Cost 5 years 4 days ago #16879

  • Syed Farhan Qadri
  • Syed Farhan Qadri's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 6
  • Thank you received: 0
Residual risk is known. We use Contigency reserves, if it occur. Management reserve is for unknown risk, which didn't identified in the Identify risk process. Hope it help you.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login