TOPIC: Module 05: Project Scope Management

Module 05: Project Scope Management 5 years 2 months ago #16596

  • Osama Mustafa
  • Osama Mustafa's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Good day
Could you please check the attached image which illustrates some facts about the scope management knowledge area.

The last two processes are part of Monitoring and Contracting Process Group, am I right?

Sincerely.
Attachments:

Module 05: Project Scope Management 5 years 2 months ago #16597

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
Osama,

Yes. Looks like you are correct. It's most likely an unintentional error.

Where did you get this text from?
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login