fbpx

Reply: EV EXAM QUESTION

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : EV EXAM QUESTION

Max. showing the last 6 posts - (Last post first)
5 years 1 month ago #16496

KRIS

's Avatar

Hi,
I got a regular email from PMP Exam Formulas.
This one was on Earned Value.
I am confused by what seem like 2 contradictory statements:
For ETC, it says:
ETC = EAC-AC
This formula is used when current EVM figures are thought to be valid and can be used to predict future performance.
But then for EAC it says:
EAC = AC+ETC
The original estimate was fundamentally flawed or conditions have changed and invalidated original estimating assumptions.
Whats the right scenario to watch out for in the exam?

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login