fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: EV EXAM QUESTION

EV EXAM QUESTION 5 years 2 months ago #16496

  • KRIS
  • KRIS's Avatar Topic Author
  • Visitor
  • Visitor
Hi,
I got a regular email from PMP Exam Formulas.
This one was on Earned Value.
I am confused by what seem like 2 contradictory statements:
For ETC, it says:
ETC = EAC-AC
This formula is used when current EVM figures are thought to be valid and can be used to predict future performance.
But then for EAC it says:
EAC = AC+ETC
The original estimate was fundamentally flawed or conditions have changed and invalidated original estimating assumptions.
Whats the right scenario to watch out for in the exam?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login