it is not correct. Close procurement is in Control Procurement process.
Project Close:
Final confirm the accepted deliveries
Issue Final report
Lesson Learned Repository
Achieve project info/docs
Update OPA
Stakeholder's evaluation project
Last step: dismiss the project team
Due to 5th and 6th version of PMP changing, a lot of training materials have not been updated. Above are I have learned /summarized from two training course materials of version 6 of PMP. Hope it is helpful!
I failed my first try in last March but PMP version was 5th, I now prepare my 2nd time try and PMP version is the 6th. Wish all the best and supper good luck to all of us who study hard and plan to pass the exam.