11 months 4 weeks ago #15954

Joe Pang

Joe Pang's Avatar

Hi Olubukola,

Using the money from contingency reserve will not require a change request because it is included in the cost baseline. So the answer is no.
1 year 2 days ago #15928

Olubukola Ogunyemi

Olubukola Ogunyemi's Avatar

Hi,

Please if project manager is to make use of part of the contingency reserve in a project, does he need to submit a change request?