TOPIC: Contingency Reserve

Contingency Reserve 8 months 1 week ago #15928

  • Olubukola Ogunyemi
  • Olubukola Ogunyemi's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 0
Hi,

Please if project manager is to make use of part of the contingency reserve in a project, does he need to submit a change request?

Contingency Reserve 8 months 4 days ago #15954

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 187
  • Karma: 12
  • Thank you received: 54
Hi Olubukola,

Using the money from contingency reserve will not require a change request because it is included in the cost baseline. So the answer is no.
Toronto-based project manager, currently engaging in paperless transformation projects for utilities companies

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily Rivera

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on August 24/25 for just $179. Click to learn more... OR Click to watch a free session...