5 years 3 months ago #15920

Anonymous

's Avatar

Thx you !!!
5 years 3 months ago #15882

Lillian Li

Lillian Li's Avatar

PMBoK P266. If it becomes obvious that the BAC is no longer viable, the project manager should consider the forecasted EAC. Once approved, the EAC may replace the BAC in the TCPI calculation.
5 years 3 months ago #15871

Cyril Galland

Cyril Galland's Avatar

Why should we use the TCPI "based on EAC" = BAC-EV / EAC-AC when our CPI is over budget ?

Doing so we will have a TCPI with the same value of the CPI (<1) and won't take any corrective actions to bring the budget back to track. Or does it imply that the EAC has been approved as the new baseline ?

Thx !!!

Cyril