Reply: Free Float

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Free Float

Max. showing the last 6 posts - (Last post first)
5 years 3 months ago #15870

Cyril Galland

Cyril Galland's Avatar

Thx you joe !!!
5 years 3 months ago #15856

Joe Pang

Joe Pang's Avatar

Hi Cyril,

You are totally correct!

Total float = LF - EF or (LS - ES)
Free float = Successor ES - Current EF
5 years 3 months ago #15839

Cyril Galland

Cyril Galland's Avatar

In the Critical Path Method shown in different books and videos, the float in the network diagram for activity is actual the total float of the activity. To know the free float of this activity, we need to subtract the early finish from this activity from the early start from the successor, correct ?
In the attached file, we can see that activity A has a total float of 2, but a free float of 1, correct ?
Thx for the help !
Cyril
Attachments: