TOPIC: Change Managment process

Change Managment process 7 years 10 months ago #15783

  • Jaafar
  • Jaafar's Avatar Topic Author
  • Visitor
  • Visitor
Dear all,

I have confused regard the change management process.

In last exam I have get “Low” in related to the change management process.

Can one support me and give me brief about the sequence of this process?

Change Managment process 7 years 10 months ago #15806

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 26
  • Thank you received: 99
Hi Jaafar,

First of all, I would suggest studying the ITTO
1) Which processes have Change Requests as outputs
2) Which processes have Approved Change Requests as inputs

Secondly, understand how a change request is evaluated and processed in the Integrated Change Control process.

Change Managment process 7 years 10 months ago #15835

  • Jaafar
  • Jaafar's Avatar Topic Author
  • Visitor
  • Visitor
Hi Joe,

Thank you for your reply.

Sorry, I will take more time from you.

When I can reject the change from the stakeholder.

which come first between these:
- Update change log
- Change request
- Evaluate the change


Thank you in advance
Moderators: Yolanda Mabutas, Markus Kopko, Mary Kathrine Padua, Professor Kevin Reilly, John Paul Bugarin, Anusha Jayaram, Harry Elston, Jean Kwanda, Neil Baghurst PMP, Elena Zelenevskaia, Erik Smith, Joseph Flanders, Pablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login