Can anyone tell what all are the Feedback techniques , Performance measurement techniques & Project review techniques in closing process.

Feedback techniques in closing process 7 years 5 months ago #15724

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 26
  • Thank you received: 99
Hi Deepak,

Not sure if I understand your question correctly, are you looking for a list of example of how to collect customer/stakeholder feedback, measure overall project performance and project review techniques?

I don't have all the examples but I can get the ball rolling:

1. Feedback
-Surveys and questionnaires
-Interviews
-Meetings (customer wrap-up)

2. Performance measurement
from PMBOK6, pg 126
-Document analysis
-Regression analysis
-Trend analysis
-Variance analysis

3. Project review
-Meetings (learns learned, close-out reporting)
-Expert Judgement
The following user(s) said Thank You: Deepak G
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMP, CSM, DFFS Black BeltElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login