fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Question on develop project charter

Question on develop project charter 5 years 5 months ago #15615

  • Deepak G
  • Deepak G's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 47
  • Karma: 1
  • Thank you received: 3
Hi,

I attempted one question in mock exam from two different sources.
Question is A project manager joins late in the execution phase of the project and figures out project charter is missing.
Source 1 says develop project charter when the project manager joins the project.
Source 2 says its too late to develop the project charter as the project is already in execution phase.

I understand that developing project charter sets the expectation and organization commitment but what to consider in above scenario as both sources are good sources for PMP mock exam.

Question on develop project charter 5 years 5 months ago #15623

  • Ty Weston, PMP
  • Ty Weston, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 207
  • Karma: 1
  • Thank you received: 37
I have to ask then, if no charter, then is there a real project? In my business, if I did not approve a project and one was being executed, it would not be well for that person.
What mock exam did you use?
The following user(s) said Thank You: Deepak G

Question on develop project charter 5 years 5 months ago #15626

  • Deepak G
  • Deepak G's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 47
  • Karma: 1
  • Thank you received: 3
That's in pmtraining demo test.

Question on develop project charter 5 years 5 months ago #15647

  • Irtaza Ghafoor
  • Irtaza Ghafoor's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 1
As my understanding should a develop charter as per PMBO Guide.
The following user(s) said Thank You: Deepak G

Question on develop project charter 5 years 5 months ago #15658

  • Steve Richards
  • Steve Richards's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 2
Hi Deepak -
If you inherit a project (and it really a project) without a project charter, then you should immediately create the project charter. Without a project charter, written and approved, you really don't have an "official" project.

I hope this helps.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login