1. The question states 'post-mortem' - > that means the project was closed.
2. At the successfull close of a project SPI should be 1.00 that is EV = PV.
3. For a successfully ended project EV cannot be greater than or less than PV.
Combining the above three - we get the reason for 'abruptly closed'.
I had the same problem with this question from Lehmann.
according to Lehmann, the answer is "1" but no justification is provided..
I still don't get what is "post-mortem analysis" tho looked it up
I was confused by this as well as 1 and 4 would appear to be valid options.
Is it number 1 because the SPi is so high (relatively speaking) that a project wouldn't be that far ahead of schedule in the real world, so must have been terminated early?
This question is from Oliver lehmann as the topic says but never mind i got the answer for it and moreover i got the PMP certifications as well yesterday. Lessons learnt are posted soon.