TOPIC: Acquire Resource vs Conduct Procurement?

Acquire Resource vs Conduct Procurement? 5 years 9 months ago #14637

  • Joe Pang
  • Joe Pang's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 24
  • Thank you received: 99
Can anyone explain the difference between the two? is it merely resource within/external to the organization?

If I am borrowing a construction worker (from another functional area within my organization) for my project, does that belong to Resource or Procurement management?
What about hiring contractors that will be working within my project team?
Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin

Acquire Resource vs Conduct Procurement? 5 years 9 months ago #14639

  • Ty Weston, PMP
  • Ty Weston, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 207
  • Karma: 1
  • Thank you received: 37
Acquiring Resources could be both internal or external. If the resource is coming from within your company, then its just acquire resource and is an assignment of some kind. Its when no resource can be found internally that you go external to the company and find someone. At that point the process shifts to a procurement process in order to contract help or gain them in some manner of negotiation.
Borrowing a worker from another area in an organisation would be acquire resource process.
Contractors imply the key word 'contract', which should inidcate that these resources are or have been acquired by a procurement process.

Acquire Resource vs Conduct Procurement? 5 years 1 week ago #17117

  • Sadri Caliskan
  • Sadri Caliskan's Avatar
  • Visitor
  • Visitor
What about the physical resources? We buy the materials in the Conduct Procurement process, so what is the purpose of Acquire (Physical) Resources? What activities are done in the Acquire Resources process in terms of physical resources?

Acquire Resource vs Conduct Procurement? 5 years 5 days ago #17134

  • Jorge Covarrubias
  • Jorge Covarrubias's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
I think they go together, Acquire physical resources may need to conduct procurement processes as you may not have them available. Usually, you can not get these resources and expense them yourself as most companies would have rules established to prevent.

The best reason I can think to justify this is: CAPEX vs OPEX, if it's officially procured, physical resource, it may be seen as CAPEX. In contrast, If you buy this and expense it will definitely be seen as an operations expense
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login