Reply: Control procurements: early termination of contract

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Control procurements: early termination of contract

Max. showing the last 6 posts - (Last post first)
5 years 9 months ago #14447

Steven Mudrinich, PMP

Steven Mudrinich, PMP's Avatar

Vinusha,

Even if the contract is terminated early, you will use the Close Procurements process as part of closing out the project.

- Steven
5 years 9 months ago #14420

Vinusha

's Avatar

Question: Since the buyer could not meet the requirements of the contract, you (the seller) want to terminate the contract early. This is done in the:

Choice 1. Plan Procurement Management process

Choice 2. Control Procurements process

Choice 3. Close Procurements process

Choice 4. Conduct Procurements process

What will be the answer? Basically, what aspects of procurements are done in close project/phase process group?