6 years 1 month ago #13557

Ty Weston, PMP

Ty Weston, PMP's Avatar

Good question. The Change Mngt Plan and Config Plan could be part of the Develop Plan process. Both are closely related to Control Scope Process as they are an input there from Develop Project Mngt Plan. A Project Plan may or may not need these plans. The Develop Project Mngt Plan Process is kind of a basket and other plans more than likely will be developed and created before the Develop PMP Process is complete. Its my opinion, that yes its done there, but it may not be in a particular order.
6 years 1 month ago #13555

Juergen Schuster

Juergen Schuster's Avatar

In which process(es) are the "Change Management Plan" and the "Configuration Management Plan" created ? In the Develop Project Management Plan itself ?
This is not very clear for me from the PMBOK guide (5) pages 76ff.

Thanks for clarification!