I noticed that the newly revised 6th Edition PMBOK ONLY addresses Triangular 3 point estimation with regard to Schedule. However, it still addresses both Triangular AND Beta distribution in the Cost section. In the past, we were typically instructed to use BETA distribution unless specifically told otherwise with regard to both time and cost estimation questions. Is this still the case? Was this purposely omitted for Schedule - in which case we should use triangular? Or was this omission in error? For Cost...then would we continue to use Beta distribution, or will it depend? Both answers have often been included as possible answers...how can we be expected to calculate correctly without knowing the preferred formula? Thoughts? Guidance? For reference RMC prep book 6th edition still includes both formulas for both sections...but they tend to include additional information for comprehensive understanding.