TOPIC: PROJECT CLOSURE/PHASE VS. HISTORICAL DATABASE

PROJECT CLOSURE/PHASE VS. HISTORICAL DATABASE 8 years 8 months ago #13349

  • NA
  • NA's Avatar Topic Author
  • Visitor
  • Visitor
Hi everyone,

I was doing a test yesterday on prepcast and this question is one tough cookie.

The question asks where we'd go to learn about the reason a project was terminated. I chose Project of Phase Closure Documents but the correct answer was Historical Database. I read PMBOK pg 104 and everything still leads me to Project Closure Documents (which I assume is a subset of the Historical Database).

Can someone explain to me what I wrote above?

Regards,

PROJECT CLOSURE/PHASE VS. HISTORICAL DATABASE 8 years 7 months ago #13366

  • Tracy Shagnea, PMP
  • Tracy Shagnea, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 134
  • Karma: 7
  • Thank you received: 46
The historical database is specifically where information on prior projects - including events such as a project being terminated - would reside. This answer is specific and thus a better response than "project closing documents" even though the historical database may have been updated in the project closure phase (and, most likely was done at this time for the project since it was terminated!).

Hope this helps!

-Tracy
Forum Moderator
PMP, CSM, M.S. Management
Moderators: Yolanda Mabutas, Markus Kopko, Mary Kathrine Padua, Professor Kevin Reilly, John Paul Bugarin, Anusha Jayaram, Harry Elston, Jean Kwanda, Neil Baghurst PMP, Elena Zelenevskaia, Erik Smith, Joseph Flanders, Pablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login