6 years 1 month ago #13176

Steven Mudrinich, PMP

Steven Mudrinich, PMP's Avatar

Saif,

The book answer is to perform a quality audit. This allows your quality management team to determine what errors in the manufacturing process are taking place, so they can be corrected. In real life it would also be important to meet with the customer to make sure that you have all of their requirements correctly identified.

- Steven
6 years 1 month ago #13126

Saif Al Juboory

Saif Al Juboory's Avatar

What would you do in this situation?
A deliverable continues to have defects that have a possibility of ending your project
e) Perform a quality audit
f) Meet with customer
g) Build a scatter diagram
h) Build an affinity diagram

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®